Coordinate transformer location, ventilation, sound, primary/secondary protection, conductors, grounding, fault current, and commissioning.
Planning
- Verify kVA, primary/secondary voltage, phase, frequency, taps, impedance, enclosure, and temperature rise.
- Evaluate room ventilation, clearances, combustibles, sound transmission, and handling path.
Key decisions
- Protection scheme and secondary-conductor arrangement.
- Grounding/bonding point and separately derived system requirements.
- Conductor routing, flexible connections, and vibration isolation.
Installation
- Set taps for the actual supply only after measurement.
- Maintain ventilation openings and service access.
- Complete bonding and terminations using listed hardware and torque values.
Commissioning & pitfalls
- Verify ratios, phase sequence, grounding, no-load/load voltage, current balance, temperature, sound, and labeling.
- Common failures: blocked airflow, wrong taps, duplicated or missing bonding, and uncoordinated secondary conductors.