Subpanel Planning Guide

Feeder, neutral isolation, grounding, access, labeling, and verification.

Treat a subpanel as feeder-supplied equipment: plan capacity, conductor system, neutral isolation, grounding, working space, and future serviceability together.

01

Planning

  • Calculate feeder load and confirm upstream capacity.
  • Choose location for access, working space, environment, and short conductor routing.
  • Confirm available fault current and panel rating.
02

Key decisions

  • Feeder conductor count and wiring method.
  • Neutral isolation from the enclosure and equipment-grounding bar.
  • Grounding-electrode requirements for a separate structure.
03

Installation

  • Keep grounded and grounding conductors on their intended bars.
  • Use listed fittings and correct connector count.
  • Torque, phase, balance, and label circuits deliberately.
04

Commissioning & pitfalls

  • Verify neutral-to-enclosure isolation, grounding continuity, feeder voltage, labeling, and directory accuracy.
  • Common failures: bonded neutral downstream, missing fourth conductor, shared neutrals handled incorrectly, and weak working space.